During Summer 2020, TLT installed over 100 General Access classrooms with simple Video Capture Classroom systems. These systems allow users to connect their laptops to the installed camera and mic through a USB interface. Once connected, users can record or videoconference using Kaltura Capture or Zoom software on their laptop.
Each room has an installed PTZ camera that can be adjusted using the included remote control. Users can set camera presets to quickly move the camera framing to different areas of the room. However, these cameras do not automatically track the subject. If your class needs close camera tracking, you may want to consider using TLT's Zoom Class Streaming service. Click here to see a description of this service, as well as other TLT support services that may be helpful to you in these classrooms.
Note: We recommend using a 6 ft. USB 2.0 cable with these systems for best results. Also, plugging in your laptop power supply may be required for your laptop to register the camera.
Note: During Summer 2023, USB inputs in these classrooms will be swapped out with the USB-B 2.0 style input. These cables will be available for checkout at the DLT Service Desk in MLIB 1705.
Video Capture Classroom Overview Video
Recording Software Information
Kaltura Capture - https://support.tlt.utah.edu/hc/en-us/articles/360004846012-How-do-I-record-a-webcam-screen-capture-video-
Zoom - https://support.tlt.utah.edu/hc/en-us/sections/360009028151-Zoom
Additional Video Capture Classrooms Information
Frequently Asked Questions - https://support.tlt.utah.edu/hc/en-us/articles/360048114372-Video-Capture-Rooms-Frequently-Asked-Questions
Video Capture Classroom Instructions - https://support.tlt.utah.edu/hc/en-us/articles/360048611071-Video-Capture-Classroom-Instructions
If you have questions or would like to set up a consultation regarding classroom video capture systems, please email classhelp@utah.edu.
Classrooms Being Installed with Video Capture Classroom Systems (Updated August 21, 2020)
Title | Status | Start date | Finish date |
AEB 320 Installation | Completed | 6/15/20 | 7/10/20 |
AEB 340 Installation | Completed | 6/15/20 | 7/10/20 |
AEB 360 Installation | Completed | 6/15/20 | 7/10/20 |
ARCH 127 Installation | Completed | 6/15/20 | 7/10/20 |
ARCH 229 Installation | Completed | 6/15/20 | 8/7/20 |
ART 158 Installation | Completed | 6/15/20 | 7/17/20 |
BEHS 101 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 102 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 109 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 110 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 111 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 112 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 113 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 114 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS 116 Installation | Completed | 6/15/20 | 7/10/20 |
BEHS Aud Installation | Completed | 6/15/20 | 7/23/20 |
Bldg 73 107 Installation | Completed | 6/15/20 | 8/21/20 |
Bldg 73 110 Installation | Completed | 6/15/20 | 8/21/20 |
Bldg 73 112 Installation | Completed | 6/15/20 | 8/21/20 |
Bldg 73 220 Installation | Completed | 6/15/20 | 8/21/20 |
Bldg 73 242 Installation | Completed | 6/15/20 | 8/21/20 |
BUC 105 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 106 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 107 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 203 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 204 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 206 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 207 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 210 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 211 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 212 Installation | Completed | 6/15/20 | 7/10/20 |
BUC 301 Installation | Completed | 6/15/20 | 7/10/20 |
CSC 25 Installation | Completed | 6/15/20 | 7/17/20 |
CTIHB 101 Installation | Completed | 6/15/20 | 7/17/20 |
CTIHB 109 Installation | Completed | 6/15/20 | 7/17/20 |
CTIHB 406 Installation | Completed | 6/15/20 | 8/21/20 |
CTIHB 459 Installation | Completed | 6/15/20 | 8/21/20 |
FASB 250 Installation | Completed | 6/15/20 | 7/17/20 |
FASB 295 Installation | Completed | 6/15/20 | 7/17/20 |
FASB 375 Installation | Completed | 6/15/20 | 8/21/20 |
FASB 388 Installation | Completed | 6/15/20 | 8/21/20 |
FMAB Aud. Installation | Completed | 6/15/20 | 7/17/20 |
GC 1560 Installation | Completed | 6/15/20 | 7/23/20 |
GC 1570 Installation | Completed | 6/15/20 | 7/23/20 |
GC 1770 Installation | Completed | 6/15/20 | 7/23/20 |
GC 1780 Installation | Completed | 6/15/20 | 7/17/20 |
GC 1825 Installation | Completed | 6/15/20 | 8/21/20 |
GC 1855 Installation | Completed | 6/15/20 | 8/21/20 |
GC 1900 Installation | Completed | 6/15/20 | 8/7/20 |
GC 2560 Installation | Completed | 6/15/20 | 8/21/20 |
GC 2575 Installation | Completed | 6/15/20 | 8/21/20 |
GC 2660 Installation | Completed | 6/15/20 | 7/23/20 |
GC 2675 Installation | Completed | 6/15/20 | 7/23/20 |
GC 2760 Installation | Completed | 6/15/20 | 8/21/20 |
GC 2900 Installation | Completed | 6/15/20 | 7/23/20 |
GC 3153 Installation | Completed | 6/15/20 | 7/23/20 |
GC 3660 Installation | Completed | 6/15/20 | 7/23/20 |
GC 3680 Installation | Completed | 6/15/20 | 7/17/20 |
GC 3700 Installation | Completed | 6/15/20 | 7/17/20 |
GC 4020 Installation | Completed | 6/15/20 | 7/23/20 |
GC 4660 Installation | Completed | 6/15/20 | 7/17/20 |
GC 4680 Installation | Completed | 6/15/20 | 7/17/20 |
GC 4700 Installation | Completed | 6/15/20 | 7/23/20 |
GC 5310 Installation | Completed | 6/15/20 | 7/31/20 |
GC 5490 Installation | Completed | 6/15/20 | 7/23/20 |
GC 5620 Installation | Completed | 6/15/20 | 7/23/20 |
GC 5680 Installation | Completed | 6/15/20 | 7/17/20 |
GC 5750 Installation | Completed | 6/15/20 | 7/23/20 |
HEB 2002 Installation | Completed | 6/15/20 | 7/31/20 |
HEB 2004 Installation | Completed | 6/15/20 | 7/31/20 |
HEB 2008 Installation | Completed | 6/15/20 | 7/31/20 |
HEB 2010 Installation | Completed | 6/15/20 | 7/31/20 |
HPR-E 206 Installation | Completed | 6/15/20 | 8/21/20 |
HPR-N 225 Installation | Completed | 6/15/20 | 7/31/20 |
HPR-N 226 Installation | Completed | 6/15/20 | 7/31/20 |
HPR-N 238 Installation | Completed | 6/15/20 | 7/31/20 |
HPR-W 117 Installation | Completed | 6/15/20 | 7/31/20 |
JFB 101 Installation | Completed | 6/15/20 | 7/31/20 |
JFB 103 Installation | Completed | 6/15/20 | 7/31/20 |
JTB 110 Installation | Completed | 6/15/20 | 7/31/20 |
JTB 120 Installation | Completed | 6/15/20 | 7/31/20 |
JTB 130 Installation | Completed | 6/15/20 | 7/31/20 |
JTB 140 Installation | Completed | 6/15/20 | 7/31/20 |
JTB 310 Installation | Completed | 6/15/20 | 7/31/20 |
JWB 335 Installation | Completed | 6/15/20 | 8/7/20 |
LCB 215 Installation | Completed | 6/15/20 | 8/7/20 |
LNCO 1100 Installation | Completed | 6/15/20 | 7/10/20 |
LNCO 1110 Installation | Completed | 6/15/20 | 7/10/20 |
LS 101 Installation | Completed | 6/15/20 | 7/31/20 |
LS 102 Installation | Completed | 6/15/20 | 7/31/20 |
LS 107 Installation | Completed | 6/15/20 | 7/31/20 |
LS 111 Installation | Completed | 6/15/20 | 7/31/20 |
MCD 130 Installation | Completed | 6/15/20 | 8/7/20 |
MEK 3550 Installation | Completed | 6/15/20 | 8/21/20 |
MLIB 1130 Installation | Completed | 6/15/20 | 8/7/20 |
MLIB 1150 Installation | Completed | 6/15/20 | 8/7/20 |
MLIB 1160 Installation | Completed | 6/15/20 | 8/7/20 |
MLIB 1170 Installation | Completed | 6/15/20 | 8/21/20 |
MLIB 1715 Installation | Completed | 6/15/20 | 8/7/20 |
ST 104 Installation | Completed | 6/15/20 | 8/7/20 |
ST 209 Installation | Completed | 6/15/20 | 8/7/20 |
ST 214 Installation | Completed | 6/15/20 | 8/7/20 |
ST 215 Installation | Completed | 6/15/20 | 8/7/20 |
SW 133 Installation | Completed | 6/15/20 | 8/7/20 |
SW 134 Aud. Installation | Completed | 6/15/20 | 8/7/20 |
WBB 820 Installation | Completed | 6/15/20 | 8/21/20 |
WEB 1230 Installation | Completed | 6/15/20 | 8/14/20 |
WEB 1248 Installation | Completed | 6/15/20 | 8/14/20 |
WEB 1250 Installation | Completed | 6/15/20 | 8/14/20 |
WEB 1450 Installation | Completed | 6/15/20 | 8/14/20 |
WEB 1460 Installation | Completed | 6/15/20 | 8/14/20 |
WEB 2250 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L101 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L102 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L103 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L104 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L105 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L110 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L114 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L120 Installation | Completed | 6/15/20 | 8/14/20 |
WEB L122 Installation | Completed | 6/15/20 | 8/14/20 |
Total: 121 projects | 6/15/20 | 8/21/20 |